The Bradley BIM Team uses this Revit Tagging and Revit Scheduling test process as part of our Quality Assurance Process prior to adding families to the Bradley Revit Library.
1) Bradley Revit Family Components are loaded into a Revit test project. (*.rvt)
2) Next, Revit families are inserted into Revit test floor plans views,Revit Specialty Equipment Tags | Plan View | Bradley Diplomat Accessories
3) We TAG each family and also test using the "Tag All Not Tagged" Revit command.
4) Tags are applied to both PLAN View and ELEVATION Views of Bradley families.
--- How to Change a Revit Family Category Designation ---
Revit Specialty Equipment Tags | Elevations | Bradley Diplomat Accessories
5) A schedule(s) is created using a Revit Plumbing Fixture or Specialty Equipment Schedule Template.
Revit Specialty Equipment Schedule | Bradley Diplomat Accessories
Images above were captured from the Bradley Diplomat Revit Family Test Project.
Visit Bradley Diplomat Toilet Accessories Product Page